CONSTRUCTION UPDATE — 28 August 2009
Construction of the Sands SkyPark’s cores is progressing to the upper roofs in the hotel towers, in preparation for the SkyPark lifting in the coming weeks.
In the South Podium, the roof steelwork is well underway in preparation for roof finishes. Concrete works are nearing completion on level 1 of the Museum and structural steelwork is progressing well. Marine works for the North Crystal Pavilion piling is completed, while the piling for the South Crystal Pavilion is still well underway.
Construction of the Sands SkyPark’s cores is progressing to the upper roofs in the hotel towers, in preparation for the SkyPark lifting in the coming weeks.
In the South Podium, the roof steelwork is well underway in preparation for roof finishes. Concrete works are nearing completion on level 1 of the Museum and structural steelwork is progressing well. Marine works for the North Crystal Pavilion piling is completed, while the piling for the South Crystal Pavilion is still well underway.
2 comments:
That looks awesome. Thanks for the update!
cool. thanks. any new updates on universal studios this week?
Post a Comment